Construction of the New Terminal

Edificio TAGSA en construcción

Construction and repairs to Guayaquil's Airport began on August 31, 2004. TAGSA hired Ekron Construcciones S.A. for the execution of the work. In the planning of the construction, AAG carried out a technical/operational audit with consultants from IATA and OACI who recommended joining both Domestic an International Terminals in a two story building. A construction of approximately 50.000m2 with an investment of ninety million dollars.

The new José Joaquín de Olmedo Airport was opened on the agreed date, complying with the concession agreement, on July 27, 2006.

In the month of July, 2014, we made the formal presentation of the Airport's expansion. With this development our Terminal now has a construction of approximately 60.000m2.